October 16
We are adding to Hastings Happenings regular updates on the Hastings-on-Hudson 2025 District-Wide Capital Improvement Project. Today, we highlight Burke Estate (Bond Prop #3).
Construction at the Burke Estate is making great strides. Recently, crews completed the installation of the turf drainage layer for inspection, and completed the upper field perimeter 12-inch storm line work. They also installed net fencing footings and goal post footings, while hauling material off-site, completing the upper field composite drain tie-ins to the storm lines. The upper field curb work has been completed. Material testing, soil inspections, and Storm Water Protection Compliance (SWPPP) inspections are also ongoing. Additionally, work has begun at the softball field, the subgrade was brought up to its designed elevation.
This week, Laura Li Construction installed the softball field’s perimeter 12-inch storm line, prepared the upper fields’ bleacher area subgrade, and completed the upper field concrete curbs. Final grading and the installation of the turf binder course will be completed.
Upcoming major work includes softball field curbs, the turf gravel infill, installation of the composite drainage system, dugout pads, backstop footings and fence posts, roadwork excavation, installation of artificial turf on Upper Burke and the softball field, and removal of extra soil.
We are on schedule for completion of construction by December 31, 2026.
The following photos give a sense of the extensive work underway.
October 30
Construction Update October 30, 2026

Work on the Upper Field continues to move forward. On Monday, October 19 five large tractor trailers delivered the new turf to the site. The following day, crews began installing the underlayment padding and the turf, starting at the South end of the field and working their way North. As of this update, the turf has been installed. The incredible amount of detail work - the layout and installation of all of the multi-field use lines,markers, lettering, numbers and the logo of our mascot, Buzz the Yellowjacket, is very near completion.
Progress has been made on the upper field bleacher area, with the ground leveled, compacted and the stone sub-base completed. The area is now ready for the next steps: building the forms and placing the concrete slab-on grade. The Upper Fields perimeter chain-link fencing has now been installed.

At the softball field, work on the retention basin has been completed, including grading, compaction, filter fabric, topsoil and seeding.
Work had begun for the concrete curbs around the softball field, starting near the backstop and working along the third-base line moving counter-clockwise around the field. The crews are currently complete with the curbs for the third base line, the batting cage, bull-pen, the outfield’s curved curbs as well as the dugout slab on grade. The Softball field’s concrete work is scheduled for completion next week.
The work for the Softball Fields turf sub-surface is in full swing. The soil sub-base has been surveyed, compaction testing and survey has been completed and the gravel and drainage system is progressing.
The installation of the site drainage structures and piping, excavation and hauling away of the excess soils continues.

November 13
Significant progress continues across our facilities projects in the past couple of weeks. As of today, we are on track to complete the Burke Estate on time, which is December 31, 2026.
At the Burke Estate Upper Field, site crews completed the turf and the detailed line work and granular infill. The low chain link fence installation is nearing completion, the electrical work, including trenching, electrical conduit installation, backfill and soil grading is in progress. The football goal posts and soccer goals have been installed. The bleacher pad is formed, braced and ready for concrete, scheduled for next week.
Turf has been completed at the baseball field bullpens as has the drainage work at the baseball field.
The softball field has seen great progress with the completion of all turf curbs, dugout slabs and bullpen curbs. The gravel sub-base, composite drains, upper gravel base and top binder course gravel has been completed, graded and compacted. Turf installation has started at the bullpens and batting cage. The foul posts have also been installed. Electrical trenching and conduit installation at the softball field is in progress.
Ongoing excess soil removal continues, as well as the installation of site drainage structures and connected piping, material testing (concrete and soil inspections), and Storm Water Protection Compliance (SWPPP) inspections (most recently conducted on 11/9/26). The small parking area near the softball field and baseball field has been brought to grade and stabilized with sub-base materials.
This past week, work shifted toward installing concrete bleacher pads across the upper, softball, and baseball fields. Crews will also complete the softball field's top binder course, begin turf installation on the softball field, and continue trenching and installing electrical conduits (followed by backfilling and grading) as well as site drainage structures and piping.